Article: West Rail opens next month: the West Rail commuter line project in Hong Kong is ahead of schedule and spectacularly under budget. It will open on September 29.(Rapid Transit: Hong Kong)
- Article from:
- International Railway Journal
- Article date:
- August 1, 2003
- Author:
CopyrightCOPYRIGHT 2003 Simmons-Boardman Publishing Corporation. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
KOWLOON-Canton Railway Corporation's (KCRC) West Rail, the largest current civil engineering project in Hong Kong, is due to open at the end of next month, more than two months ahead of the original target date. It has also come in well under budget at $HK 46.4 billion ($US 5.9 billion), compared with an original estimate of $HK 64 billion.
Pre-operational trial running, in which trains run to the schedule of revenue operations, started in June and was due to last for three months. Testing and commissioning West Rail's various systems reached a peak in late April with round-the-clock test runs averaging about six full train trips per hour between the northern ...