Article: Kennedy Center: Improvements Needed to Strengthen the Construction Process.
- Article from:
- General Accounting Office Reports & Testimony
- Article date:
- October 1, 2003
CopyrightCOPYRIGHT 2003 Stonehenge International. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
GAO-03-1141T September 10, 2003
In the mid-1990s, John F. Kennedy Center for the Performing Arts (Kennedy Center) officials recognized a need for additional parking and better site access. As a precursor to a planned project to construct an 8-acre plaza and two additional buildings at the site, the Kennedy Center is currently in the process of constructing a garage expansion and site improvement project. Because of congressional concerns over project delays and costs as well as challenges the Kennedy Center faces as it pursues this major construction effort, GAO was requested to examine (1) the garage expansion and site improvement project's current costs, time ...