Article: Brown Line stirs CTA rift: Board chief warns Kruesi over new cost overruns.
- Article from:
- Chicago Tribune (Chicago, IL)
- Article date:
- July 21, 2006
CopyrightCOPYRIGHT 2006 Chicago Tribune. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
Byline: Jon Hilkevitch
Jul. 21--The public has lost confidence in the management of the Brown Line rehab project, CTA Chairwoman Carole Brown said Thursday, warning amid disclosure of new cost overruns and slippage in the construction schedule that transit agency President Frank Kruesi would be held personally responsible.
"We have a huge credibility problem," Brown said after the board approved a station renovation contract that is $16 million more than the original engineering estimate.
The overall Brown Line project, involving 18 stations, is running 11 percent above the CTA's construction budget, resulting in the agency burning through ...