Article: MODCOMP awarded contract by Virginia Power -- utility plant upgrade to open-systems -- meets company needs for next 15 years.
- Article from:
- Business Wire
- Article date:
- March 5, 1997
CopyrightCOPYRIGHT 1997 Business Wire. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
FORT LAUDERDALE, Fla.--(BUSINESS WIRE)--March 5, 1997--Virginia Power has awarded MODCOMP a $967,000 contract to upgrade and retrofit the Plant Control and Monitoring System (PCAMS) SCADA computer system at its Bath County Pumped Storage Station, located in Bath County, Va.
The Bath County Pumped Storage Station, which went into commercial operation in December 1985 with MODCOMP CLASSIC(r) superminicomputers and MODACS(tm) I/O equipment, has six turbine generators with a capacity of 2,100 megawatts. Sixty percent of the capacity is owned by Virginia Power and 40 percent of the capacity is owned by Allegheny Power System. The Virginia Power owned capacity ...