Article: South Africa: ARM Assmang Khumani 10 million tonne per annum iron ore mine completed.
- Article from:
- TendersInfo
- Article date:
- August 13, 2009
CopyrightCOPYRIGHT 2009 Al Bawaba (Middle East) Ltd. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
Byline: pinto03
Assmang Limited, which is jointly controlled by African Rainbow Minerals and Assore Limited, announced that the 10 million tonne per annum Khumani Iron Ore Mine has been completed on time and within budget.
It also said that the ARM and Assore Board of Directors have approved additional CAPEX of ZAR 5.5 billion for the completion of the Khumani Expansion Project, to increase Khumani`s capacity from the current level of 10 million tonne per annum to 16 million tonne per annum.
The estimated total CAPEX for the proposed Khumani Expansion Project is ZAR 6.7 billion based on the feasibility study completed in June 2009, which ...