he South Miami-Dade Cultural Arts Center is two years behind schedule and stalled amid construction errors. If this sounds like a familiar refrain, it should.
It is the sequel to downtown Miami's performing arts center, a horror story of a construction project that ended two years past deadline and millions over budget.
Only this time the scene has moved 30 miles south to Cutler Bay, where the $47 million South Miami-Dade Cultural Arts Center, a sort of mini-PAC, languishes in mid-construction nearly two years after it was scheduled to be complete and with no opening date set.
Delays have played out amid familiar ...