The US Nuclear Regulatory Commission has issued an Early Site Permit (ESP) and Limited Work Authorization (LWA) to Southern Nuclear Operating Company for the Vogtle ESP site near Augusta, Georgia.
Successful completion of the ESP process resolves many site-related safety and environmental issues, and determines the site is suitable for possible future construction and operation of a nuclear power plant. The LWA allows a narrow set of construction activities at the site. Southern Nuclear filed its ESP application Aug. 15, 2006, and filed its LWA request on Aug. 16, 2007, seeking permission for construction activities limited to placement ...