Article: Town manager asks Aquarion to `sit down and negotiate'; Judge denied company's request for a preliminary injunction.(LOCAL NEWS)
- Article from:
- Telegram & Gazette (Worcester, MA)
- Article date:
- September 16, 2009
CopyrightCOPYRIGHT 2009 Worcester Telegram & Gazette. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
Byline: Ellie Oleson
OXFORD - Selectmen learned last night that Worcester Superior Court Justice Richard T. Tucker has denied Aquarion Water Co.'s request for a preliminary injunction.
Aquarion had asked the court to declare the company "entitled to be compensated" for the proposed replacement of approximately 1,000 feet of water main on Main Street at an estimated cost of $315,000. The company had also asked the court to order the town "to place sufficient funds in escrow to pay for the water main replacement."
In a decision filed Sept. 8, the judge said that Aquarion had not proven "that the Main Street water main replacement project is ...