Article: T.Y. Lin International Completes Unprecedented Roll-in/Roll-out of Bay Bridge Yerba Buena Island Detour in Record Time.

T.Y. Lin International / Moffatt & Nichol (TYLI/M&N) Joint Venture made history on Tuesday, September 8, with the completion of construction on the East Tie-In (ETI) portion of the Yerba Buena Island (YBI) detour, a steel truss temporarily supported by 150-foot steel towers that serves as a transition section connecting the eastern span of the San Francisco-Oakland Bay Bridge to the YBI Tunnel. TYLI/M&N served as the designer and construction engineer on this historic project.

Installing the 3,600-ton double-deck steel truss was performed 150 feet above ground and entailed a sequence in which workers removed an existing section of the Bay Bridge using a skid bent ...

Related newspaper, magazine, and journal articles:

 
 
Newsweek Harper's Magazine The Washington Post Chicago Tribune Crain's Chicago Business PRNewswire Pediatric News The Nation Advertising Age The Economist (US) A FREE trial gives you access to over 80 million articles! Access over 6,500 publications with a FREE trial!