Article: T.Y. Lin International Completes Unprecedented Roll-in/Roll-out of Bay Bridge Yerba Buena Island Detour in Record Time.
- Article from:
- Journal of Engineering
- Article date:
- October 7, 2009
CopyrightCOPYRIGHT 2009 NewsRX. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
T.Y. Lin International / Moffatt & Nichol (TYLI/M&N) Joint Venture made history on Tuesday, September 8, with the completion of construction on the East Tie-In (ETI) portion of the Yerba Buena Island (YBI) detour, a steel truss temporarily supported by 150-foot steel towers that serves as a transition section connecting the eastern span of the San Francisco-Oakland Bay Bridge to the YBI Tunnel. TYLI/M&N served as the designer and construction engineer on this historic project.
Installing the 3,600-ton double-deck steel truss was performed 150 feet above ground and entailed a sequence in which workers removed an existing section of the Bay Bridge using a skid bent ...