Article: Israel: No further bids in NIS 2b Soreq desalination project.
- Article from:
- TendersInfo
- Article date:
- October 6, 2009
CopyrightCOPYRIGHT 2009 Al Bawaba (Middle East) Ltd. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
The tender to build and operate the 150 million cubic meter a year Soreq desalination plant has been closed, with three consortia submitting bids in the NIS 2 billion project. The tenders committee will now review the bids, a process that is due to take two to three months.
When the winner is announced, the process for securing financing will begin, which will take a year. Construction can then get underway. For the first time in tenders of this kind, the contract permits earthworks for the project to begin subject to significant progress in securing the financing, which means that construction could begin in 2010.
The Soreq desalination plant is due to ...