Adani Power Ltd (APL) announced that it would expand capacity at the under-construction thermal power project in Tiroda, Maharashtra, to 3,300 MW.
The initial plan was to produce 1,980 MW. The change envisages a total investment of nearly Rs 14,000 crore.
The company had collected Rs 3,016.52 crore via the capital market in July-August. The investment made until September 30 was Rs 1,667.86 crore, temporary investments in interest-bearing liquid instruments were Rs 1,216.11 crore and bank balance was at Rs 132.55 crore, according to unaudited results for the last three and six months.
The Tiroda plant is the first ...
Related newspaper, magazine, and journal articles:
|
|
Article: 3i India Infra Fund invests Rs 900 cr in Adani ...
PTI - The Press Trust of India Ltd.;
October 25, 2007 ;
605 words
... ... investment was made in Adani Power, a wholly-owned subsidiary ... Company Ltd last April. Adani Power is presently developing an independent 2,640 MW imported coal-based ... issued said here today. Adani Power is a fully-owned subsidiary ...
|
|