Article: Canada: Ontario Bruce 1 & 2 reactor restarts delayed.
- Article from:
- TendersInfo
- Article date:
- November 5, 2009
CopyrightCOPYRIGHT 2009 Al Bawaba (Middle East) Ltd. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
Byline: kusumv03
TransCanada Corp on Wednesday said the return of the 750-megawatt Units 1 and 2 at the Bruce A nuclear power station in Ontario would be delayed until mid 2011 for Unit 2 and about four months later for Unit 1.
Previously Bruce said the units would return in 2010. A spokesman at TransCanada, which released its earnings Wednesday, said the company would answer questions about Bruce later this morning on a conference call.
In the earnings release, TransCanada said as of Sept. 30, 2009, Bruce had incurred about C$3.1 billion in costs for the refurbishment of Units 1 and 2 and work was about 75 percent complete.
...