Article: Tampa Bay Water Board Approves Contract For Regional Surface Water Treatment Plant.
- Article from:
- PR Newswire
- Article date:
- April 11, 2000
CopyrightCOPYRIGHT 2000 PR Newswire Association LLC. This material is published under license from the publisher through the Gale Group, Farmington Hills, Michigan. All inquiries regarding rights should be directed to the Gale Group. (Hide copyright information)
|
CLEARWATER, Fla., April 11 /PRNewswire/ --
A team led by USFilter was awarded a 15-year contract to design, build and operate (DBO) a 60-million-gallon per day, state-of-the-art regional surface water treatment plant for Tampa Bay Water.
Tampa Bay Water's board of directors approved the $135 million agreement, one of the largest water treatment DBO contracts in the United States and an essential component of Tampa Bay Water's plan to meet the region's need for new water supplies. The contract includes approximately $79 million in capital costs and $56 million in operation and maintenance fees over the initial 15-year term and a five year option period. ...