Article: New U. Toledo residence hall's opening pushed back one year
- Article from:
- University Wire
- Article date:
- August 28, 2000
- Author:
CopyrightProvided by ProQuest LLC. (Hide copyright information)
|
Jenny Cole
University Wire
08-28-2000
(The Collegian) (U-WIRE) TOLEDO, Ohio -- On Oct. 6, students and faculty will be cautioned to "watch [their] step," as construction of the new residence hall begins, said Norman Koenigseker, interim director of capital projects and space planning.
While this October date has been planned since last year, the completion date was delayed by a year, Koenigseker said. The $32 million co-ed residence hall, which is still in the design process, was originally to be completed by fall 2001. It is now expected to open its doors by fall 2002.