Article: Primary Petroleum Completes 3D Seismic Program on its Teton Prospect in Montana
- Article from:
- CCNMatthews Newswire
- Article date:
- October 30, 2007
CopyrightCopyright 2007 CCNMatthews Newswire. Provided by ProQuest LLC. (Hide copyright information)
|
CALGARY, ALBERTA--(Marketwire - Oct. 30, 2007) - Primary Petroleum
Corporation ("Primary" or the "Company") (TSX VENTURE:PIE) is pleased
to announce that its 19.11 sq. mi. 3D seismic program has been
completed on the Teton oil prospect in Western Montana. The program
has been completed on time and on budget.
Data processing has commenced with interpretation to follow. It is
anticipated that it should take up to 3 to 4 weeks to complete the
selection of the initial 8 drill locations. Primary expects that
based on early rig availability and minimal delays with title
confirmation and permitting, drilling could commence in early
December.
The Teton prospect covers some 97,400 net acres (152 ...