Article: CITY DOCK

A mere six months ago, boardwalks and brick were ripped from Annapolis' City Dock in an effort to revamp the popular landmark.

And now an end is finally in sight for the $9 million project, which replaced the dock's nearly 1,000-feet of bulkheads, boardwalk and brick.

Crews have been pretty much working around the clock in double shifts to complete the job by the April 15 wrap-up date.

Replacement of the wooden boardwalk and paving of the portion of street in front of Susan B. Campbell Park were finished up this week, with only the electrical wiring and clean-up left to be completed, said Harry Sandrouni, a city civil engineer heading the project.

With warmer weather typically comes cranes ...