Renovations at the Pitchfork Records building on North Main
Street are under way at last.
"I'm absolutely delighted construction's finally taking place,"
said Pitchfork Records owner Michael Cohen.
Both Main Street Concord and the city have been trying to work
with building owner Evangelos Lillios for several years to improve
the building's facade. One of Concord's most conspicuous downtown
buildings is marred by broken bricks and worn paneling. It has
frequently been described as an eyesore.
Lillios has attributed the delay to difficulties finding a
contractor to do the work for a reasonable price. Contractors say
Lillios is difficult to deal with. One recently left the job after
fighting ...
Related newspaper, magazine, and journal articles:
|
|
Article: Well, that's Gilbert and George for you
The Independent - London;
August 26, 1995 ;
700+ words
...So that you can meet Gilbert and George, two of Britain's best- known and best-pa...Or how about plain old Fucked Up? These are from Gilbert and George's "Dirty Words" show of 1977. Gilbert and George have their reasons, imperfectly valid...
|
|