The Army Corps of Engineers will likely delay the start of flood
control work in the Turtle Creek Valley until mid-October, its
spokesman said.
Allegheny County still needs two easements to work on creekside
property, causing a slight delay that corps officials had
anticipated. They had planned to award a contract by early August
and start in September but said months ago that getting real estate
easements is always a big obstacle and could delay the project.
For residents, danger still lingers, said Rebecca Bradley,
manager of Wilkins, one of several towns along Thompson Run that had
major damage during a June flood. Debris and sediment still linger
in the creek, making it more vulnerable ...