Article: What a mess

DETAILS of the mismanagement of a North-East town centre redevelopment - which left taxpayers facing a [pounds]780,000 bill for a gas pipe blunder - are revealed today.

The Pedestrian Heart scheme, in Darlington, ran into costly delays in January 2006, when contractors hit a 100-year-old cast iron gas main, buried in a shallower trench than plans had indicated.

The entire pipeline was rerouted, adding [pounds]780,000 to the cost, disrupting the town centre and delaying the scheme by four months.

Councillors commissioned Ward Hadaway solicitors to review the project and advise the authority on whether or not legal action could be taken against either contractor to recoup any of the money.

The ...