MILLERSBURG -- As the county inches toward a ground breaking for
the construction of the Walnut Creek wastewater treatment facility,
the commissioners received word the equipment for the facility could
cost 20 percent less than estimated.
Holmes County Sanitary Engineer Chris Young met with
commissioners Thursday and discussed the bids the engineering firm
ATS Engineers received for the facility's new equipment.
Young said the original estimate was almost $1.1 million. However
one firm's bid was about $200,000 less than the estimate.
"They are going to doublecheck this week and make sure everything
is what it seems to be," Young said.
The approval of the treatment ...