The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:
Wisconsin Public Service Corporation
Project No. 2595-103
ORDER APPROVING REQUEST FOR AN EXTENSION OF TIME TO FILE FINAL OPERATION EVALUATION REPORT
On January 31, 2006, Wisconsin Public Service Corporation (licensee) filed a request for an extension of time to file the final operation evaluation report for the High Falls Hydroelectric Project No. 2595 as required by paragraph (B) of the March 3, 2004, Order Approving Revised Operational Compliance Plan Under Article 403. Article 403 requires the licensee, in part, to complete a three year evaluation period to determine ...