Article: KENTUCKY PUBLIC SERVICE COMMISSION ISSUES ORDER REGARDING APPLICATION OF CUMBERLAND VALLEY ELECTRIC TO PASS-THROUGH INCREASE OF ITS WHOLESALE POWER SUPPLIER
- Article from:
- US Fed News Service, Including US State News
- Article date:
- April 2, 2007
CopyrightCopyright © HT Media Ltd. All Rights Reserved. Provided by ProQuest LLC. (Hide copyright information)
|
The Kentucky Public Service Commission issued the following order:
In the Matter of:
APPLICATION OF CUMBERLAND VALLEY ELECTRIC, INC. TO PASS-THROUGH AN INCREASE OF ITS WHOLESALE POWER SUPPLIER PURSUANT TO KRS 278.455(2) )
CASE NO. 2006-00477
INTERIM ORDER
On January 29, 2007, Cumberland Valley Electric, Inc. ("Cumberland Valley") submitted an application to pass-through any wholesale rate adjustment granted to East Kentucky Power Cooperative, Inc. ("EKPC") in Case No. 2006-00472. Cumberland Valley submitted its application pursuant to the authority of KRS 278.455(2) and 807 KAR 5:007, Section 2. By letter dated February 1, 2007, Cumberland Valley was informed that its application was not ...