The Nuclear Regulatory Commission issued the following notification received:
Power Reactor
Facility: MONTICELLORegion: 3 State: MNUnit: [1] [ ] [ ]RX Type: [1] GE-3NRC Notified By: ROBERT SCHREIFELSHQ OPS Officer: MARK ABRAMOVITZ
REACTOR SCRAM WITH STUCK OPEN MAIN TURBINE CONTROL VALVES
"At 1528 hours Central Time, a RPS trip occurred, all rods fully inserted. Turbine valve testing was in progress. A group 1 isolation occurred with all MSIVs closing. A partial group 2 occurred due to low reactor water level. All safety systems (valves) operated correctly. Currently reactor pressure/cooldown in progress using HPCI in pressure control, normal condensate and ...