Article: FERC ISSUES ORDER TO TOWN OF MASSENA, NEW YORK REGARDING DIRECTOR'S FORMAL DISPUTE RESOLUTION DETERMINATION
- Article from:
- US Fed News Service, Including US State News
- Article date:
- January 17, 2008
CopyrightCopyright © HT Media Ltd. All Rights Reserved. Provided by ProQuest LLC. (Hide copyright information)
|
The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:
Project No. 12607-001 - New YorkMassena Grasse River Hydroelectric ProjectTown of Massena, New York
Mr. Andrew J. McMahonTown of Massena Electric Department71 East Hatfield StreetMassena, NY 13662
Reference: Director's formal dispute resolution determination
Dear Mr. McMahon:
Pursuant to section 5.14(l) of the Commission's regulations implementing the Integrated Licensing Process, this is my determination on the study dispute filed by the New York State Department of Environmental Conservation (New York DEC) on November 9, 2007, with respect to the study plan for the ...