Article: FERC ISSUES ORDER TO TEXAS EASTERN TRANSMISSION REGARDING APPROVAL FOR NEW AND RELOCATED TEMPORARY EXTRA WORK SPACES
- Article from:
- US Fed News Service, Including US State News
- Article date:
- February 26, 2008
CopyrightCopyright © HT Media Ltd. All Rights Reserved. Provided by ProQuest LLC. (Hide copyright information)
|
The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:
In Reply Refer To:
OEP/DG2E/Gas 1Texas Eastern Transmission, LPCedar Bayou Lateral ProjectDocket No. CP07-411-000
February 26, 2008Garth JohnsonGeneral Manager, Certificates and ReportingTexas Eastern Transmission, LPP.O. Box 1642Houston, TX 77251
Re: Approval for New and Relocated Temporary Extra Work Spaces
Dear Mr. Johnson:
I approve your February 21, 2008 request for Texas Eastern Transmission, LP (Texas Eastern) to relocate and add temporary extra work space as described in your filing. These extra work spaces are necessary for the realigned bores associated with ...