Article: FERC ISSUES ORDER TO CORPUS CHRISTI, CHENIERE CORPUS CHRISTI PIPELINE ET AL. REGARDING REQUEST FOR AN EXTENSION OF TIME

The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:

In Reply Refer To:OEP/DPC/CB-2

Corpus Christi LNG, L.P.

Docket No.CP04-37-000

Cheniere Corpus Christi Pipeline, L.P.

Docket No.CP04-44-000Sec. 375.308(w)(4)

Ms. Lisa M. ToneryMs. Tania S. PerezCounsel for: Corpus Christi LNG, L.P.Cheniere Corpus Christi Pipeline, L.P.Fulbright & Jaworski L.L.P.666 Fifth Avenue, 31st FloorNew York, New York 10103-3198

RE: Request for an Extension of Time

Dear Ms. Tonery:

On April 18, 2005, the Commission issued an Order Granting Authority Under Section 3 of the Natural Gas Act and Issuing Certificates (the Order), in Docket Nos. ...