The Wisconsin Department of Transportation issued the following news release:
Work began July 28 on a cofferdam in advance of the reconstruction of County A at Lake Delton, according to the Wisconsin Department of Transportation (WisDOT).
Governor Jim Doyle last week signed a $1.08 million emergency contract to install a cofferdam near the planned embankment of the new roadway. The cofferdam is necessary to restrict the flow water into the work zone before road construction can begin.
James Thieding Construction, Inc. of Loganville is the prime contractor for the cofferdam. Construction includes placement of aggregate and sheet piling and removal of two partial buildings. Thieding ...