Article: FERC ISSUES ORDER TO PUBLIC SERVICE COMPANY OF COLORADO AMENDING LICENSE BY DELETING TRANSMISSION LINE, REVISING ANNUAL CHARGES
- Article from:
- US Fed News Service, Including US State News
- Article date:
- November 24, 2008
CopyrightCopyright © HT Media Ltd. All Rights Reserved. Provided by ProQuest LLC. (Hide copyright information)
|
The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:
Public Service Company of Colorado Project No. 2351-011
ORDER AMENDING LICENSE BY DELETING TRANSMISSION LINE AND REVISING ANNUAL CHARGES
On June 17, 2008 Public Service Company of Colorado (PSC), licensee for the Cabin Creek Pumped-Storage Project, FERC No. 2351 filed an application to amend its license. The licensee is requesting Commission approval to delete from the license a 31-mile-long double-circuit 230-kV transmission line. The project is located on the South Clear Creek and its tributary Cabin Creek in Clear Creek County, Colorado, and occupies U.S. Forest Service ...