The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:
In Reply Refer To:
OEP/DG2E/LNGC
Dominion Cove Point LNG, L.P.
Docket No. CP05-130-000
Sec. 375.308(x)
December 17, 2008
Ms. Anne E. Bomar
Vice President, Federal Regulation
Dominion Cove Point LNG, L.P.
701 East Cary Street
Richmond, VA 23219
RE: Authorization to Commence Service
Dear Ms. Bomar:
I grant your December 10, 2008 request to commence service from the Cove Point Expansion Project at your LNG import terminal near Cove Point, Maryland. Your request is in compliance with environmental condition 11 in the Commission Order Issuing Certificates and Granting Section 3 ...
Related newspaper, magazine, and journal articles:
|
|
Article: FERC ISSUES ORDER TO DOMINION COVE POINT ...
US Fed News Service, Including US State News;
September 18, 2008 ;
613 words
... ... Pursuant to Sec. 375.307Dominion Cove Point LNG, LPDocket No. RP08-509-000 Dominion Cove Point LNG, LP120 Tredegar StreetRichmond ... Verdun: On August 15, 2008, Dominion Cove Point LNG, LP filed the referenced ...
|
|