Article: FERC ISSUES ORDER TO CENTRAL POWER REGARDING PETITION FOR TEMPORARY WAIVER OF OPERATING STANDARD
- Article from:
- US Fed News Service, Including US State News
- Article date:
- November 8, 2009
CopyrightCopyright © HT Media Ltd. All Rights Reserved. Provided by ProQuest LLC. (Hide copyright information)
|
WASHINGTON, Nov. 6 -- The U.S. Department of Energy's Federal Energy Regulatory Commission issued the text of the following delegated order:
Central Power & Lime, LLC
Docket Nos. EL09-76-000
QF82-207-006
Skadden, Arps, Slate, Meagher & Flom LLP 1440 New York Ave., N.W. Washington, D.C. 20005-2111
Attention: Glenn J. Berger, Esq. Donna M. Byrne, Esq. Aryan Moniri, Esq. Attorneys for Central Power & Lime LLC
Reference: Central Power & Lime, LLC - Petition for Temporary Waiver of Operating Standard for Qualifying Cogeneration Facility
Dear Messrs. Berger and Moniri and Ms. Byrne:
On September 15, 2009, Central Power & Lime LLC (CP&L) filed a petition for a temporary ...